A garage conversion ADU in Monrovia typically runs $45,000 to $130,000 and takes four to seven months from the first demolition swing to the final inspection. You’re turning an existing structure into a legal, permitted living space, so the number depends mostly on how far the plumbing, electrical and structural work has to travel from where it sits today. Call (888) 271-7872 and we’ll walk the garage with you and put a real number in writing.
How the work actually runs, stage by stage

People ask us all the time what happens after the contract gets signed. Here’s the honest sequence, with the durations we usually see on a Monrovia garage job.
Stage 1 – Planning and permits (4 to 8 weeks). Before anything gets torn out, we confirm the garage is a legal conversion candidate, pull the property’s records, and prepare drawings. In the Old Town grid the design-review path can add time here, so this stage runs longer than it would a few miles east. You’ll decide the floor plan and the exterior treatment at this point, because both feed the submittal.
Stage 2 – Demolition and shell prep (3 to 5 days). The garage door comes out, the opening gets framed in, and we strip the interior back to framing. This is when we find out what the slab and existing walls are really like. On older bungalows near Myrtle Avenue, that first week often turns up settled slab corners or termite damage that wasn’t visible in the walkthrough, and we price that work with you before moving forward. No surprise line items appearing after the fact.
Stage 3 – Foundation, framing and utilities (3 to 5 weeks). If plumbing has to run to the converted space, we saw-cut the slab, trench and tie into the main. Electrical gets a new subpanel or panel upgrade, and the walls get insulated and sealed. The decision you make here is where the kitchenette and bathroom sit, which is really a decision about how far your supply and waste lines travel.
Stage 4 – Rough inspections and close-up (2 to 3 weeks). Framing, electrical, plumbing and mechanical inspections happen before drywall goes on. Then insulation, drywall, texture and paint. You’ll typically pick finishes during this window: flooring, cabinet fronts, fixtures, paint.
Stage 5 – Trim, systems and final walkthrough (3 to 4 weeks). Cabinets and countertops install, the bathroom tile goes in, HVAC ties in, and we do a final punch walk with you. The city signs off, and your garage is a permitted dwelling. The 730-Day Done Right Promise backs every bit of it.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll be making along the way
A garage conversion isn’t a single product, it’s a stack of decisions. Here’s what actually matters and how each option trades off.
- Bathroom position: A half bath near the existing drain line is the cheapest route. A full bath with a shower adds roughly $9,000 to $28,000 depending on how far the waste line has to go. Tenants expect a full bath, so most Monrovia conversions go that way when the slab allows.
- Kitchenette vs. full kitchen: A sink, counter and small cooktop keeps the utility run short and lands at the lower end. A full kitchen with an exhaust vent, dedicated circuit and range pushes toward the high end. The quieter move for a rental is a compact kitchenette; the louder move is full self-contained.
- Heating and cooling: A ductless mini-split is the go-to here, because running ductwork through a garage shell is awkward and the unit handles the foothill temperature swings well. Central ties into the house system but costs more and complicates the electrical load.
- Flooring: Luxury vinyl plank over the slab is durable, handles the moisture that creeps up through older concrete, and costs less than engineered hardwood. Tile reads cooler underfoot and is the better choice if the space stays rented.
- Exterior treatment: Matching the existing stucco and roofline reads as “original house,” which matters in the historic review areas. A distinct material cue is often easier to permit but shows the space is new.
- Insulation and ventilation: A garage shell insulates and ventilates differently than a house wall. We spec a sealed, well-vented assembly so the unit doesn’t trap moisture or overheat in summer.
For the finishes that make the space feel like home, homeowners often pair this with Cabinets & Countertops in Monrovia and Backsplash, Tile & Flooring in Monrovia, since those are the visible pieces of a finished unit.
What Garage Conversion ADU costs in Monrovia, CA

Most Monrovia garage conversions land between $45,000 and $130,000, with the middle of that range being a full-bath, kitchenette, mini-split unit on a typical single-car or two-car-garage footprint. A bare-bones studio conversion with no plumbing runs at the low end. Five things move the number.
- Size of the garage: A 200-square-foot single stall is one story; converting a 400-square-foot two-car garage adds finish and systems cost roughly in proportion.
- Existing slab and framing: Settled or cracked slabs and termite-damaged framing drive up the structural repair line. Older Monrovia stock tends to have both.
- Distance to utilities: Trenching to the main drain and running a new electrical feed are the two biggest swing factors.
- Material grade: Cabinet fronts, countertops, fixtures and flooring each have a low and a high version. The gap between them can be $15,000 or more.
- Permit and review scope: Historic design review and hillside site considerations add both time and cost to the front end.
Your written estimate should spell out demolition, framing, utilities, insulation, drywall, finishes, permits and final inspection, itemized by trade, so you can see exactly where your money goes. Things that typically sit outside the base contract and get quoted separately: major slab foundation repair, a full electrical panel replacement, and any landscape or site work around the garage. Upfront pricing means the number you see is the number you pay. From foundation to finish line, one contractor handles the whole thing.
See the difference
Before
After
Before
After
Before
AfterWhat Monrovia homes specifically do to this job
Monrovia sits right against the San Gabriel Mountains at the base of Angeles National Forest, and that geography shapes garage conversions here in ways it doesn’t in Duarte or Baldwin Park. The flat Old Town grid below the ‘L’ street line is full of 1920s-era Craftsman and Spanish Colonial bungalows on clay and expansive soils, so the slab under an old garage is often the first thing we examine and the first thing that needs work. Settled corners, underslab moisture and cracked slabs are routine findings in the 91016 ZIP. In the foothills above, slope and retaining walls change the calculus, and if the garage sits on a graded lot the structural review gets more involved. The Old Town core around Myrtle Avenue carries design-review and historic-preservation constraints that a more central municipality in the SGV doesn’t enforce as strictly, so if your garage fronts a historic block, the permit path runs a different route than a same-size job a few streets over. Wildfire hardening matters too: Class A roofing, ember-resistant vents and defensible space come up on almost every foothill conversion, and we spec for them rather than treating them as an add-on.
Serving Monrovia, CA – Our Local Coverage Area
We serve Monrovia and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Monrovia

Plan on four to seven months from contract signing to final inspection. The build itself is typically ten to fourteen weeks; the front end (design, permit and review) eats the other weeks, and the historic review path in Old Town adds time to that front end. Call (888) 271-7872 for a timeline against your specific garage.
Yes. A garage conversion ADU is a legal dwelling unit and requires permits and inspections for the structural, electrical, plumbing and mechanical work. We pull the permits and manage the inspections. Skipping them creates a real problem when you sell or rent the unit, so we don’t cut that corner.
Yes. A studio-style conversion with no bathroom or with a compact half bath keeps the plumbing run short and pulls the price toward $45,000. If the waste line is already nearby, a full bath is still an affordable add; if it’s clear across the slab, expect the higher figure.
The range runs $45,000 to $130,000 depending on size, existing condition, utility distances and finish level. Our written estimate is itemized by trade with no change orders, and projects over $10,000 get $1,000 off, with 0% financing for 18 months available. Call (888) 271-7872 for an exact quote.
Every Garage Conversion ADU we build is covered by our 730-Day Done Right Promise, one of the longer workmanship guarantees in residential construction. If it’s not done right, we make it right. Calls are answered by a live person 24/7, and every technician who shows up is background-checked and in uniform.
Get a free estimate for your Monrovia garage conversion
If you’re thinking about converting your garage into a rentable or family ADU, start with a free on-site estimate. Call (888) 271-7872, and a live person answers, day or night. We’ll walk the garage, check the slab and existing framing, talk through your options, and hand you an itemized written quote with the full scope spelled out. No voicemail, no waiting until Monday. This is often part of a wider scope, so if you’re also weighing a larger addition, our Home Additions & ADU in Monrovia page covers the full picture, and our Home Additions & ADU service hub covers the broader work. We handle projects across Monrovia and the surrounding foothill communities.
Written by the team at Groundwork Construction Co.