Tub-to-Shower Conversion in Whittier: What It Costs and How Long It Takes
A tub-to-shower conversion in Whittier usually runs $3,500 to $10,000 and takes 5 to 10 working days, depending on whether we’re keeping the drain where it is or moving it. The job means removing the tub and its surround, protecting the waterproofing and framing underneath, and rebuilding the wet area as a curbless or low-curb shower with new tile, a new pan, and fixtures. Most single-bathroom jobs finish in about a week. Call (888) 271-7872 for a free on-site estimate.
How the Conversion Actually Runs, Day by Day
This is the sequence we follow on nearly every tub-to-shower conversion in Whittier, and we walk you through it before the first hammer swings.
- Day 1 – Demo and discovery. The tub and surround come out, along with the old backer board and any rotten framing behind it. Older Whittier homes – the 1900s to 1930s Craftsmans near Uptown especially – often have surprises behind a tub wall: old plaster, corroded drain fittings, or a valve that needs replacing. We photograph everything so you see what we see.
- Days 2-3 – Rough plumbing and framing. If the drain or supply lines are moving, this is when it happens. We set the valve at the right height for your new shower, re-frame the alcove, and bring the walls flat and square. You decide here on niche placement, bench or no bench, and curb height.
- Days 3-4 – Waterproofing. Here’s where cheap jobs go wrong. We install a sloped mud pan or a pre-formed shower base, then a bonded waterproof membrane on the walls and floor, then flood-test the pan before a single tile goes up. Waterproofing is not the fun part. It’s the part that decides whether your shower lasts 15 years or 3.
- Days 4-8 – Tile and fixtures. You’ve already picked the tile by this point, so we set it, grout it, and install the shower head, valve trim, and glass. This is the stage with the most visible progress.
- Days 8-10 – Seal, punch list, walkthrough. We seal, clean up, and do a final inspection with you running the water and checking every edge. Any touch-ups get scheduled before we call it done.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make Before Tile Goes Up
Conversions succeed or fail on three decisions: how you waterproof, what tile you set, and whether to enlarge the footprint. Here’s the honest trade-off on each.
- Shower pan style. A pre-formed acrylic or fiberglass pan is the cheapest and fastest – around $300 to $700 for the pan itself – and it’s fine for a rental or a quick flip. A tiled mud pan with a bonded membrane adds labor but looks custom and holds up better over time.
- Waterproofing system. A surface-applied membrane like a Schluter Kerdi system adds a few hundred dollars in materials and maybe a half-day of labor, but it’s the difference between a shower that dries out and a shower that grows mold behind the tile.
- Tile. Porcelain or ceramic in the $3 to $8 per square foot range is durable and low-maintenance. Natural stone – marble, travertine – costs more and needs sealing, and in Whittier’s hard water it will show soap scum if you don’t stay on top of it.
- Curb vs. curbless. A curbless shower means dropping the floor joists or building up the surround, which adds cost and complexity. It’s the accessible choice for homeowners planning to age in place.
- Glass. A frameless glass panel runs $400 to $1,200 installed and is the single biggest visual upgrade per dollar in the room.
If your conversion is part of a full Bathroom Remodeling in Whittier, we coordinate the tile and fixture selections so the shower doesn’t fight the rest of the room.
What Tub-to-Shower Conversion Costs in Whittier, CA

Here’s the number up front: $3,500 to $10,000 for a standard tub-to-shower conversion in Whittier, with the typical job landing near $6,000. The low end covers a straight swap in a standard alcove with stock tile and a pre-formed pan. The high end covers a larger footprint, custom tile work, a bench, a niche, and frameless glass.
Four things actually move that number:
- Plumbing relocation. Keeping the drain and valve where they sit keeps you near the low end. Moving the drain to the center of a larger footprint adds $800 to $2,000.
- Existing condition behind the wall. Rotten framing, an undersized valve, or old galvanized supply lines get caught at demo and add days and dollars. We price this possibility into the estimate rather than surprising you later.
- Material grade. Porcelain vs. marble, acrylic pan vs. tiled mud pan, framed vs. frameless glass. A wide swing in materials moves the total by $2,000 or more.
- Permit scope. A permit is generally required when plumbing or structural work is involved and typically adds a few hundred dollars. We pull it and pass the inspection.
Every estimate we write is a line-item written quote – the number you see is the number you pay. No change orders that creep. Our service is backed by the 730-Day Done Right Promise, so if something isn’t right, we come back and fix it.
See the difference
Before
After
Before
After
Before
AfterWhat Whittier’s Housing Stock Does to This Job
Whittier is a built-out, older first-ring LA suburb, so most of the tub-to-shower conversions we run here are teardowns of 1950s and 1960s bathrooms in the postwar tract homes across the east and south sides, ZIP codes 90601 and 90604 among them. Those tubs were set in a 30-inch alcove with steel drain lines and copper supply stubs that are now 60 years old – so we plan for valve replacement and drain work even when the plan starts as a cosmetic swap.
If your home is in Uptown Whittier or one of the designated historic structures along the Greenleaf and Philadelphia corridor, plan a little more lead time: interior work inside a bathroom usually stays clear of the exterior design-review process, but if your shower project involves replacing an exterior window or venting through the wall, the city’s historic review can come into play. We flag that before demo, not after. And in the 1900s-era Craftsman homes near uptown, we regularly find original knob-and-tube era wiring feeding an old vent fan – a code issue that has to be corrected while the wall is open, so budget for it.
The summer heat and Santa Ana wind days also shape our schedule: we try not to run demo of exterior-facing walls on high-wind days, and we keep dust containment tight through the summer because Whittier’s dry air lets dust travel farther than you’d expect. Homeowners sometimes pair this work with Tile Roofing in Whittier and Metal Roofing in Whittier when the project grows to the full envelope. Our bathroom remodeling service across Whittier handles the whole house if you want one contractor Bathroom Remodeling from demo to finish.
Serving Whittier, CA – Our Local Coverage Area
We serve Whittier and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Tub-to-Shower Conversion in Whittier

A typical tub-to-shower conversion in Whittier takes 5 to 10 working days from demo to walkthrough, with most single-bathroom jobs finishing in about a week. If we’re moving plumbing or dealing with discovery behind the wall, plan on the longer end. Call (888) 271-7872 for a site visit and a firm schedule.
Yes, a permit is generally required when the shower involves plumbing changes or structural work, and it’s often needed for tile and waterproofing scope per the city’s inspection requirements. We pull the permit and manage the inspection as part of the job. Call (888) 271-7872 to talk through your specific project.
Yes, in most cases we keep the existing drain and valve location, which keeps the project near the low end of the $3,500 to $10,000 range. Moving the drain or enlarging the footprint adds cost and days. We confirm what’s possible during the free on-site estimate.
The range is $3,500 to $10,000, with a typical job around $6,000. The biggest cost drivers are plumbing relocation, condition behind the wall, tile and pan material grade, and glass. Call (888) 271-7872 for an exact line-item quote – estimates are free.
The 730-Day Done Right Promise covers every tub-to-shower conversion we install. If it’s not done right, we make it right. Call (888) 271-7872 to schedule your free on-site estimate and see the written warranty terms before you sign anything.
Get a Free Tub-to-Shower Conversion Estimate in Whittier
Call (888) 271-7872 to schedule a free on-site estimate for your tub-to-shower conversion in Whittier. We’ll walk the bathroom, check the drain and valve setup, talk through tile and pan options, and leave you with a written line-item quote – no vague ballpark. Calls are answered by a live person, day or night. Financing is available at 0% for 18 months, and projects over $10,000 get $1,000 off.